**DATES ARE SUBJECT TO CHANGE**

SEGMENT 1
South 2nd Street - FINISHED


SEGMENT 2 
South Park Place - FINISHED


SEGMENT 3
East Main Street and South Third Street - FINISHED

SEGMENT 4
West Main Street and North Third Street - FINISHED

SEGMENT 5
North Park Place and North Second Street - FINISHED
 

SEGMENT 6  - currently in progress

Click here for map of current closure (through Monday, November 20, 2017)

Click here for closure map to begin Monday, November 20, 2017.

  • The State Route 13/Mount Vernon Road bridge over State Route 16 will open to two-way traffic on Friday, November 17, 2017, after the 3:00 PM ribbon cutting ceremony.

  • Church Street and the portion of North 3rd Street, between North Park Place and the alley north of Church Street, are also scheduled to open on Friday, November 17, 2017.

  • Beginning Monday, November 20, 2017, the North 3rd Street closure will extend north through the Locust Street intersection.

  • Hudson Avenue will be closed between Locust Street and the State Route 16 westbound ramp.

  • Locust Street and Hudson Avenue are scheduled to open in March, 2018.

  • The portion of North 3rd Street, between Locust Street and the alley north of Church Street, is scheduled to open on May 1, 2018.